Construction Update

July 14, 2016

The past week’s construction activities included placing reinforcing steel and concrete for the South pier columns, attaching bracing to the steel girders for the span between the North abutment and North pier (See Photo), continued work on the last section of retaining wall adjacent to the South abutment, and the start of backfilling around the South abutment. Next week’s work is anticipated to include the delivery of more steel girders, setting reinforcing and placing concrete for the South pier cap, removal of the north extension of the temporary work platform, and miscellaneous site work including backfilling behind the South abutment.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Watch the Bridge Demolition!