Construction Update

November 13, 2015

The pile driving operation at Abutment A was completed this week (See Photo) as well as continued progress on the temporary work platform adjacent to the existing truss spans. The completion of the pile driving operation will lead to the start of formwork for the concrete footing at Abutment A in the early part of next week. Other work scheduled to be happening in the next week include water main installation at the South end of the project and of course more temporary work platform progress.


Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction


Project Contacts

Ed Roberge, P.E.
Concord City Engineer

Gene McCarthy, P.E.
McFarland Johnson Project Manager

Project Overview