Construction Update

April 21, 2016

This past week’s construction activities included delivery of reinforcing cages and steel casings for the two piers to be constructed in the river, setting formwork and the beginning to place reinforcing steel for the North abutment stem and lower pilasters (See Photo), building the South extension to the temporary work platform, and excavating for the retaining wall along the south edge of the river. Work anticipated to occur next week includes the start of construction on the North pier columns, placing reinforcing for the North abutment stem and lower pilasters, continued work on the South extension to the temporary work platform.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Watch the Bridge Demolition!