Construction Update

May 23, 2016

The past week’s construction activities has included the completion of the South extension to the temporary work platform, placement of concrete for the upper pilasters at the North abutment (See Photo) and a component of the North Pier foundation, and continued construction of the retaining wall along the river on the South side of the project. Work anticipated for next week includes setting reinforcing and pouring concrete for the East wingwall of the North abutment, placement of concrete for a component of the North Pier foundation, and the completion of the East section of the retaining wall along the river on the South side of the project.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Watch the Bridge Demolition!