Construction Update

January 29, 2016

Construction activities last week included installing formwork for the South abutment backwall, placing stone fill in front of the location where the new North abutment will be located (See Photo), finalizing the main temporary work platform, beginning work on the North extension of the temporary work platform, and preparing several sections of the existing truss for removal. It is anticipated that next week several sections of the existing truss will be removed, concrete for the South abutment backwall will be placed, and the stone fill slope in front of the new north abutment will be completed.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Project Overview