Construction Update

June 29, 2016

The past week’s construction activities included the delivery of several sections of the steel girders, removing the formwork to expose the new North concrete pier (See Photo), continued progress on the South pier foundation and backfilling around the North abutment stem and wingwalls. Next week’s work is expected to include the arrival of more steel girders, placement of concrete for the final section of the South pier foundation, construction of the last section of retaining wall adjacent to the South abutment, and construction of the South Pier columns.

 

Project Schedule

March 2014

NEPA Approval

September 2014

Begin Final Design

December 2014

Finalize Permits

May 21, 2015

Advertise for Construction

July 15, 2015

Project Award

July 20, 2015

Notice to Proceed

August 3, 2015

Begin Construction

 

Project Contacts

Ed Roberge, P.E.
Concord City Engineer
603.225.8520 eroberge@concordnh.gov

Gene McCarthy, P.E.
McFarland Johnson Project Manager
603.225.2978
gmccarthy@mjinc.com

Watch the Bridge Demolition!